Friday, April 10, 2015

work progress photos MAC/APRIL2015

My work progress photos MAC/APR 15







Street lighting pole on the bridge leading to DOT 2 already fixed 





HT cabling work in progress
From CS2 to TNB sub


Ball valves for VH2 already fixed partially
pending other connections to it including to actuators.



Street lighting pole 5M height installation in progress on dam crest.




Street lighting pole used
LYCORPOLE



Tx pretest in progress
SAT.
Tx used - AMSGB












Will update monthly photos to track the M&E progress..

New target to handover stage 1 - end of MAY 15, i doubt it, will not be able to get the permanent supply.

ISSUES.

  • until now UDS not appointed will definitely effect permit from JKR and cable laying work by TNB. TNB already reuested this several times..
  • Permit will take months as well as TNB work.
  • will appeal TNB to start sub work first.
  • Interfacing work on super structure for DOT2 & VH2 not completed until now, roller shutters/wall need to be fixed before electrical works can be carried out there.
  • OHTC also need to be installed.
  • Other civil and mechanical interfacing works too..., on crest, VH2, DOTS, access road, road works and so on.
  • ht switchgears, battery charger, compact sub stations yet to be sent to site. FAT about to be done for DC charger and compact sub. HT sgrs k done.
  • FAT for DB, SB,SSB all need to be done and sent to site after that.
  • Catalogues/brochures for lighting to be installed yet to be sent to site.